Work Commenced on December 2000 and Completed on August 2002. The Plant was designed to produce 10,000 tpy Zinc Ingot by electrolytic process.
Engineering design in all disciplines and supply of equipment and machineries for whole plant units Covering the following plant areas:
– Leaching area
– Purification area
– Electrowinning area
– Magnesium bleed off and waste water treatment area
– Melting and Casting area
– Reaction and filtration
– Residue pond
– Lead recovery from Leach residues
– Process and control room buildings
– Construction of all plant units include Civil works, erection and installation of equipment and machineries
Client | Qeshm Zinc Smelting Complex Co |
Project | Construction of Zinc Plant |
Location | Qeshm Island (IRAN) |
Services | Basic and Detailed Engineering, supply of equipment and machineries, supply of spare parts, implementation of Civil work, erection and installation of equipment and machineries, Commissioning of the plant |